The NVRRWP is a collaborative partnership that includes the
Cities of Modesto, Turlock, Ceres, the Del Puerto Water District, and Stanislaus County.
City of Modesto
City of Turlock
City of Ceres
Stanislaus County
Del Puerto Water District

Construction

The First Phase (Modesto's Component) of the NVRRWP construction is now complete. This phase included a new pump station at the City of Modesto's Jennings Water Quality Control Plant, 7 miles of 42-inch pipeline and an outfall structure at the Delta Mendota Canal (DMC). The project alignment is shown in the graphic below.

construcion project

Milestone - December 27, 2017

  • The project is now delivering recycled water produced by the City of Modesto's recycled water facilities.

Milestone - June 30, 2018

  • Construction is complete of the First Phase (Modesto's portion) of the NVRRWP.

Milestone - July 24, 2018

  • The City of Turlock awarded the construction contract for the Second Phase (Turlock Component) of the NVRRWP, to Ranger Pipelines.
construcion project